Marshfield I-44 Interchange Project at MM 103
Update for Week of December 30

  • No work planned from noon on New Year’s Eve until 9 a.m. Thursday, Jan. 2, during the New Year’s holiday.

Work Scheduled:  

  • Hauling rock and dirt to build areas on north side of I-44
  • Relocating utility lines in various locations
  • Clearing trees and brush in various locations

Traffic Impacts:  

  • ROAD CLOSED: Brinkley Road (I-44 north outer road) CLOSED east of Webster County Route W
    • Signed detour: Webster County Route W, Vinyard Road and Rusty Road
    • Brinkley Road closed until fall 2020
  • No other traffic impacts expected

 (Weather or construction delays could alter the work schedule.)
 
Project Summary:

  • Build a new bridge to take  Webster County Route CC over I-44 at Mile Marker 103
  • Relocate Webster County Route CC at Rifle Range Road to intersect with I-44
  • Build interchange ramps so drivers safely exit and enter I-44 at Webster County Route CC
  • Build roundabouts at either end of interchange to connect with Brinkley Road/I-44 outer road on the west and Marshall Road/Route CC on the east
  • Route CC between Rifle Range Road and Route 38 in Marshfield turned over to the city of Marshfield after completion of interchange project
  • Prime Contractor: H.R. Quadri Contractors, LLC of Van Buren
  • Completion Date: June 2021. However, the interchange will be open to traffic by December 31, 2020.
  • Total Project Cost: $16.4 million
  • Sign up for project updates!